The Digital Strategy Task Force report recommended that CU Denver complete a classroom audit that could inform a roadmap for technology upgrades in order to ensure appropriate classroom technology for teaching across modalities.
To facilitate more timely upgrades, CU Denver will use temporary staff to complete the next set of classrooms during the Spring 2025 semester and into Summer 2025. The team will work with the registrar’s office to coordinate classroom relocations. Classrooms with outdated distance learning hardware will be upgraded with tier 2 technology (marked with an asterisk) to ensure capabilities in rooms meet current needs/demands.
Preliminary Relocation Schedule for Spring 2025
Move classes into room 1500 April 28th-May 16th
Rooms to Upgrade
Phase 4 will begin in Spring 2025 and continue through Fall 2025 with the following tasks:
Phase 1 included initial data gathering and collecting feedback about cross-disciplinary classroom needs. An audit of CU Denver owned classrooms was conducted by Corey Parham, Assistant Director of Service Delivery and Operations in Denver’s Office of Information Technology. The initial data collection was guided by the following questions:
On November 1, 2022, Corey Parham and Katie Linder presented preliminary findings from data collected on the 96 CU Denver classrooms and discussed some possible next steps for the classroom technology audit project. For those not able to attend, a recording of the session can be found below.
Phase 2 of the project moved from data gathering and planning to implementation. Based on feedback from faculty members in phase 1 of the project, a tiered structure was developed for classroom upgrades (see table below). This tiered structure represents basic upgrades for all classrooms (tier 1) and more advanced upgrades (tier 2) that may be applied to some classrooms based on institutional need.
The first 23 CU Denver owned classrooms will be upgraded to tier 1 in the summer 2024. After gathering additional feedback, the exact number of tier 1 and tier 2 classrooms will be determined during phase 3.
*Larger classrooms will be equipped with dual projectors and projection screens
A proof-of-concept room for tier 2 upgrades was installed to demonstrate the capabilities used in hybrid and distance learning. Additional feedback on tier 2 technology will be gathered in phase 3 (see more below). If you would like to test out the new classroom technology, please use EMS (schedule.ucdenver.edu) to schedule North Classroom, Room 1405. This room features:
The project leads worked with facilities, faculty and administration to determine funding and determine a plan for the classroom technology upgrades. The first 23 classrooms upgraded were in the North Classroom. The upgrades took place during summer 2024. These classrooms were upgraded with tier 1 technology.
Katie Linder, PhD | Associate Vice Chancellor | Academic Innovation and Strategy | Executive Sponsor |
Doug Sicker, PhD | Vice Chancellor | Office of Information Technology | Executive Sponsor |
Corey Parham | Assistant Director of Classroom and AV Operations | Office of Information Technology |
Crystal Gasell, EdD | Director of Academic Technology and Training | Division for Teaching Innovation and Program Strategy |
Desiree Shroyer | Project Manager | Office of Information Technology |